Budgeting, Fund Management and Allocation, Expenditure Approval and Tracking of Funds Committed and Expended - Lessons Learned from Major Programs
July 31, 2008 | Author: PM Hut | Filed under: Cost Management, Lessons Learned, Program Management
Budgeting, Fund Management and Allocation, Expenditure Approval and Tracking of Funds Committed and Expended - Lessons Learned from Major Programs (#32 in the series Foundations, Frameworks and Lessons Learned in Program Management)
By Robert Prieto
The lessons learned on several major programs have been characterized in the context of the program management framework elements previously described. These lessons learned are reflected below.
The programs reflected range from $ 1 to over $ 30 billion in size and from 4 to 30 years in duration and include both US and non-US program management delivery. Over $ 125 billion of program cost is represented by these major programs. Program management lessons learned have been “sanitized” to protect the identity of specific programs. Input derives from program managers or other senior executives and in select instances from lessons learned documents prepared as part of the post mortem process.
Lessons Learned on Budgeting, Fund Management and Allocation, Expenditure Approval and Tracking of Funds Committed and Expended - #3 in Organizational Foundation & Integrated Framework Processes
Program 1: Integrate “earned value” measurements with the control system. Implement training and discipline early so that the process is instilled in the program culture. Maintain effective ‘checks and balances’ through routine audits and exception reviews
Program 2: Integration of cost, schedule, construction and all other framework processes is necessary to effectively plan and manage the program.Centralized control systems are necessary to avoid a multi-project approach with hidden risks and costs.
Program 3: Expenditure approval processes must support decision making time frames.
Program 4: Establish comprehensive project controls and management information systems at project initiation.
Program 5: Centralized control functions (cost, schedule, QA) need to be established at the outset of the program and not layered on later, once problems have developed.
Program 6: Many entities tried to control funds flow and as a result extensive schedule delays occurred and price escalation was a problem. PM kept track of funding and onerous reporting requirements were a barrier to efficient program execution. Reporting was a major function of the integrated team because of the intense interest in the program. A web-based system was used that satisfied most clients desiring information. The system was installed late so maximum benefit was not realized.
Program 7: Centralized program/project controls need to be comprehensively implemented and attention paid to multi-project cost and schedule factors.
Program 8: No lessons learned.
Program 9: No lessons learned.
Program 10: Funds held by owner and financial accounting done by them. Financial management of program and projects were monitored and managed by PM. Balance proved effective. Reporting was standardized and put on a web site that allowed those with the proper access credentials to view real time data on program progress. This included jobsite cameras which provided current progress photos continually.
Program 11: No lessons learned.
Robert Prieto, Senior Vice President
Robert Prieto is senior vice president for Fluor, where he leads strategy for Fluor’s Industrial and Infrastructure group. Mr. Prieto focuses on the development and delivery of large, complex projects worldwide.
Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. As head of PB’s board of directors, he was responsible for overseeing management performance, establishing top-level policies, and ensuring the firm’s continued long term success.
He is a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the board of directors of the Business Council on International Understanding, a member of the board of the Civil Engineering Forum for Innovation, and co-founder and member of the board of the Disaster Resource Network. He currently serves on the National Research Council’s committee framing the challenges on Critical Infrastructure Systems. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He is also a member of the board of trustees of Polytechnic University of New York, and was previously selected as alumni of the year by its New York Chapter.
He has had an executive sponsorship role in the World Trade Center Transportation Hub; West Coast Rail Modernization; Train Protection and Warning System; Level 3 Communications Long Haul Network and Superconducting Super Collider.
Prieto holds a master of science in nuclear engineering from Polytechnic University of New York and a bachelor of science in nuclear engineering from New York University.
Fluor Corporation (NYSE: FLR) provides services on a global basis in the fields of engineering, procurement, construction, operations, maintenance and project management. Headquartered in Irving, Texas, Fluor is a FORTUNE 500 company with revenues of $14.1 billion in 2006. For more information, visit www.fluor.com.
Related Articles
No comments yet.
feel free to leave a comment
Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!
XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
All fields marked with " * " are required.