Cost Estimating in Program Management

August 26, 2008 | Author: PM Hut | Filed under: Cost Estimating, Cost Management, Lessons Learned, Program Management

Cost Estimating in Program Management (#39 in the series Foundations, Frameworks and Lessons Learned in Program Management)
By Robert Prieto

The lessons learned on several major programs have been characterized in the context of the program management framework elements previously described. These lessons learned are reflected below.

The programs reflected range from $ 1 to over $ 30 billion in size and from 4 to 30 years in duration and include both US and non-US program management delivery. Over $ 125 billion of program cost is represented by these major programs. Program management lessons learned have been “sanitized” to protect the identity of specific programs. Input derives from program managers or other senior executives and in select instances from lessons learned documents prepared as part of the post mortem process.

Lessons Learned in Cost Estimating - #10 in Organizational Foundation & Integrated Framework Processes

Program 1: Integrate risk analysis with cost estimating, a process that integrates contingencies into activity cost and time.

Program 2: No lessons learned.

Program 3: Cost estimates must accurately reflect current market conditions as well as prospective trends. Competition for key resources is increasingly global in nature. Additionally, the distorting effect of implementing a large program in a remote of resource constrained area.

Program 4: No lessons learned.

Program 5: No lessons learned.

Program 6: Fast track nature of the program can drive program manager to build upon cost estimating done by the main general contractors. Estimates so developed must be negotiated with the contracts managers to ensure adequacy and correctness. Final agreed amount should be a not to exceed figure with a fixed scope. Changes can be made that affect price but approval of the integrated team must be required.

Program 7: No lessons learned.

Program 8: No lessons learned.

Program 9: No lessons learned.

Program 10: Conceptual cost estimating must be done by an integrated owner/ PM team to make sure that the entire program is delivered within the funds available. Relying on designer or constructor estimates for individual projects is not good enough to maintain the required program control.

Program 11: No lessons learned.

Robert Prieto, Senior Vice President

Robert Prieto is senior vice president for Fluor, where he leads strategy for Fluor’s Industrial and Infrastructure group. Mr. Prieto focuses on the development and delivery of large, complex projects worldwide.

Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. As head of PB’s board of directors, he was responsible for overseeing management performance, establishing top-level policies, and ensuring the firm’s continued long term success.

He is a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the board of directors of the Business Council on International Understanding, a member of the board of the Civil Engineering Forum for Innovation, and co-founder and member of the board of the Disaster Resource Network. He currently serves on the National Research Council’s committee framing the challenges on Critical Infrastructure Systems. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He is also a member of the board of trustees of Polytechnic University of New York, and was previously selected as alumni of the year by its New York Chapter.

He has had an executive sponsorship role in the World Trade Center Transportation Hub; West Coast Rail Modernization; Train Protection and Warning System; Level 3 Communications Long Haul Network and Superconducting Super Collider.

Prieto holds a master of science in nuclear engineering from Polytechnic University of New York and a bachelor of science in nuclear engineering from New York University.

Fluor Corporation (NYSE: FLR) provides services on a global basis in the fields of engineering, procurement, construction, operations, maintenance and project management. Headquartered in Irving, Texas, Fluor is a FORTUNE 500 company with revenues of $14.1 billion in 2006. For more information, visit www.fluor.com.

Share this article:
  • Digg
  • del.icio.us
  • Facebook
  • Google
  • blogmarks
  • LinkedIn
  • Reddit
  • StumbleUpon
  • TwitThis
  • Yahoo! Buzz

Related Articles

No comments yet.

feel free to leave a comment

Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

All fields marked with " * " are required.

Project Management Categories