Crossing the Desert Syndrome

October 31, 2007 | Author: PM Hut | Filed under: Project Management Best Practices

Crossing the Desert Syndrome
By Johanna Rothman

I’m close to falling into “Crossing the Desert” syndrome. A project team focuses on an interim milestone, works like the devil to meet that milestone. They meet the milestone, look up, and realize they’re not at the end of the project–they still have to finish the darn thing. They’re living the Crossing the Desert syndrome.

The problem with focusing on an interim milestone (and too typically doing lots of overtime, late nights, weekends to meet the milestone) is that the team is burnt out once they’ve met the interim milestone. And you still need them to finish the project.

If you’re a PM in this position, encourage people to take some time off. If they haven’t been taking weekends, and if they’ve been working overtime, have people go back to a regular 40-hour week. NO extra time. If they’ve missed some holidays or vacation, have them take time now. You need people who have brain cells left in their heads, not people who are about to–or already have–made stupid mistakes.

Be prepared for people to be a bit down, even after they’ve met the milestone. Because they pushed so hard, they may not be able to see how much progress they made, or how good the product is. They may only be able to focus on what they didn’t do. You may need to be a bit of a cheerleader.

You may need to replan the rest of the project. If people had to work like crazy to meet an interim date, chances are good that the rest of the schedule is too aggressive, too. Gather everyone in a conference room, hand them all yellow stickies, and ask them to organize how they can finish the rest of the project.

Make sure you acknowledge their hard work, refocus them on the last part of the project, and good luck.

Johanna Rothman consults, speaks, and writes on managing high-technology product development. Johanna is the author of Manage It!’Your Guide to Modern Pragmatic Project Management’. She is the coauthor of the pragmatic Behind Closed Doors, Secrets of Great Management, and author of the highly acclaimed Hiring the Best Knowledge Workers, Techies & Nerds: The Secrets and Science of Hiring Technical People. And, Johanna is a host and session leader at the Amplifying Your Effectiveness (AYE) conference (http://www.ayeconference.com). You can see Johanna’s other writings at http://www.jrothman.com.

Share this article:
  • Digg
  • del.icio.us
  • Facebook
  • Google
  • blogmarks
  • LinkedIn
  • Reddit
  • StumbleUpon
  • TwitThis
  • Yahoo! Buzz

No comments yet.

feel free to leave a comment

Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

All fields marked with " * " are required.

Project Management Categories