Design Estimates in Construction Project Management
March 17, 2009 | Author: PM Hut | Filed under: Cost Estimating, Cost Management
Design Estimates in Construction Project Management (#15 in the Hut Project Management for Construction)
By Chris Hendrickson
In the planning and design stages of a project, various design estimates reflect the progress of the design. At the very early stage, the screening estimate or order of magnitude estimate is usually made before the facility is designed, and must therefore rely on the cost data of similar facilities built in the past. A preliminary estimate or conceptual estimate is based on the conceptual design of the facility at the state when the basic technologies for the design are known. The detailed estimate or definitive estimate is made when the scope of work is clearly defined and the detailed design is in progress so that the essential features of the facility are identifiable. The engineer’s estimate is based on the completed plans and specifications when they are ready for the owner to solicit bids from construction contractors. In preparing these estimates, the design professional will include expected amounts for contractors’ overhead and profits.
The costs associated with a facility may be decomposed into a hierarchy of levels that are appropriate for the purpose of cost estimation. The level of detail in decomposing the facility into tasks depends on the type of cost estimate to be prepared. For conceptual estimates, for example, the level of detail in defining tasks is quite coarse; for detailed estimates, the level of detail can be quite fine.
As an example, consider the cost estimates for a proposed bridge across a river. A screening estimate is made for each of the potential alternatives, such as a tied arch bridge or a cantilever truss bridge. As the bridge type is selected, e.g. the technology is chosen to be a tied arch bridge instead of some new bridge form, a preliminary estimate is made on the basis of the layout of the selected bridge form on the basis of the preliminary or conceptual design. When the detailed design has progressed to a point when the essential details are known, a detailed estimate is made on the basis of the well defined scope of the project. When the detailed plans and specifications are completed, an engineer’s estimate can be made on the basis of items and quantities of work.
Next in the Hut Project Management for Construction:
Bid Estimates in Construction Project Management
Previously in the Hut Project Management for Construction:
Types of Construction Cost Estimates
Chris Hendrickson is the Duquesne Light Company Professor of Engineering and Co-Director of the Green Design Institute at Carnegie Mellon University. His research, teaching and consulting are in the general area of engineering planning and management, including design for the environment, project management, transportation systems, finance and computer applications. Prof. Hendrickson is a Distinguished Member of the American Society of Civil Engineering, an Emeritus Member of the Transportation Research Board and a Fellow of the American Association for the Advancement of Science. Hendrickson is also the recipient of many professional awards.
Related Articles
No comments yet.
feel free to leave a comment
Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!
XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
All fields marked with " * " are required.