Earned Value Management for Absolute Beginners

May 7, 2009 | Author: PM Hut | Filed under: Uncategorized

Earned Value Management for Absolute Beginners
By Mike Griffiths

Let’s imagine our project is to build a wall around a garden.

Our Project - Build a wall around a garden

For simplicity, let’s assume 4 equal sides and a budget of $200 per side. Our schedule is one side per day so we should finish in 4 days with a cost of $800.

Here is how the project progresses:

Our Project - Front wall is complete (Day 1)

Day 1 Progress: Front wall completed and the budget of $200 spent – perfect!

Our Project - Side 1 Started (Day 2)

Day 2 Progress: Side 1 started, but the foundations had to go deeper than expected using more materials so the side was not quite completed and the spend was $220

Our Project: Side 2 started (Day 3)

Day 3 Progress: Side 1 was finished, only half of the back wall was built, but the team left early and only spent $140 that day

So are we ahead or behind? How much over/under budget are we?

This is the type of thing that happens on real projects, some things go fine; other things go slower than anticipated and before long you need to determine, on balance, how much ahead or behind from the original plan you are.

Just from common sense we can tell we are behind, by the end of day 3 we should have finished 3 sides not 2.5.

Spend wise, we can make some estimates too; we have achieved 2.5 out of 4 sides which is 62.5% (2.5 / 4 *100 = 62.5) of the overall project. We have spent $200 + $220 + $140 = $560 of the $800 which is 70% (560/800 *100 = 70) of the budget. Having spent 70% of your budget and only achieved 62.5% of your budgetted progress indicates you are spending faster than anticipated.

Congratulations you now understand the basics of Earned Value!

Earned Value has some unique terminology that throws off lots of people, but none of it is too complicated, here are the terms:

Earned Value Terms

Term Name Meaning
PV Planned Value Estimated value of the work planned to be done
EV Earned Value Estimated value of the work actually accomplished
AC Actual Costs Actual Costs Incurred
BAC Budget At Completion Amount budgeted for total project
EAC Estimate At Completion Currently expected total for project
ETC Estimate To Complete How much more to finish
VAC Variance At Completion How much over/under we expect to be

Using the above terms, we get the following values for our example above (at the end of day 3):

Term Name Meaning Day 3 values
PV Planned Value Estimated value of the work planned to be done $600
EV Earned Value Estimated value of the work actually accomplished $200+$200+$100=$500
AC Actual Costs Actual Costs Incurred $200+$200+$140=$540
BAC Budget At Completion Amount budgeted for total project $800
EAC Estimate At Completion Currently expected total for project ?
ETC Estimate To Complete How much more to finish ?
VAC Variance At Completion How much over/under we expect to be ?

To fill in the remaining fields we need some formulae, again don’t be put off by the terminology, it is really quite easy:

Earned Value Forumlae

Name Formula Meaning
Cost Variance CV = EV - AC -ve = over budget, +ve = under budget
Schedule Variance SV = EV - PV -ve = behind schedule, +ve = ahead of schedule
Cost Performance Index CPI = EV / AC I am getting “x” cents out every $
Schedule Performance Index SPI = EV / PV I am progressing at “x”% originally planned
Estimate At Completion EAC = BAC / CPI As of now, how much do we expect the total project to cost
Estimate To Complete ETC = EAC - AC How much more to finish
Variance At Completion VAC = BAC - EAC How much over/under we expect to be

The first two values (Cost Variance and Schedule Variance) are measures of how much ahead or behind cost and schedule we are. Just remember negative values here are negative signs for the project, it means we are over budget or behind schedule.

The next two values (Cost Performance Index and Schedule Performance Index) are factors where the value 1 means on budget or schedule, anything below 1 means behind, anything above 1 means ahead.

So plugging in our numbers we get:

Name Formula Meaning and Value
Cost Variance CV = EV - AC $500 - $560 = -$60 (we are over budget)
Schedule Variance SV = EV - PV $500 - $600 = -$100 (we are behind schedule)
Cost Performance Index CPI = EV / AC $500 / $560 = 0.89 (I am getting 89 cents out of every $)
Schedule Performance Index SPI = EV / PV $500 / $600 = 0.83 (I am progressing at 83% of the rate originally planned)
Estimate At Completion EAC = BAC / CPI $800 / 0.89 = $900 (The total is now likely to be $900)
Estimate To Complete ETC = EAC - AC $900 - $560 = $340 (From now I will likely spend $340)
Variance At Completion VAC = BAC - EAC $800 - $900 = -$100 (We expect to be $100 over budget)

So we can estimate that at this rate it is more likely to cost $900 rather than the $800 budget and given we are only progressing at 83% of the rate we first estimated, this will now take 4.8 days to finish (original 4 days / 0.83 rate of progress = 4.82).

That is it, no quantum mechanics necessary. Negative Variance figures are generally bad as are performance indexes below 1. There are other formulae, and alternative formulae that can be used in certain circumstances, but these are the basics.

All of these numbers were available to us in our initial common sense assessment of progress. Having completed only 2.5 sides instead of 3 by the end of day 3 gives us the 2.5/3 = 0.83 Schedule Performance Index (SPI) we calculated. Likewise spending $560 and only building $500 worth of original plan work is our 500/600 = 0.89 Cost Performance Index (CPI)

Download Earned Value Management Cheat Sheet Courtesy of Mike Griffiths - Leading Answers

Mike Griffiths is an independent consultant specializing in effective project management. Mike was involved in the creation of DSDM in 1994 and has been using agile methods (Scrum, FDD, XP, DSDM) for the last 13 years. He serves on the board of the Agile Alliance and the Agile Project Leadership Network (APLN). He maintains a leadership and agile project management blog at http://www.LeadingAnswers.com

Share this article:
  • Digg
  • del.icio.us
  • Facebook
  • Google
  • blogmarks
  • LinkedIn
  • Reddit
  • StumbleUpon
  • TwitThis
  • Yahoo! Buzz

Related Articles

4 people have left comments

Thanks so much for this article. This has helped me understand EVM for the exam. KISS is always better than long technical jargon. I have shared this article with other potential PMP’s and instructors.

Stacia wrote on May 8, 2009 - 12:26 pm | Visit Link

Hi Mike, please re check the EAC formula. The calc looks fine.

peter wrote on May 9, 2009 - 6:55 am | Visit Link

Peter,

You’re absolutely right, I have fixed the EAC formula (for the records, it was an editing mistake on PM Hut’s side, not Mike’s).

PM Hut wrote on May 9, 2009 - 10:11 am | Visit Link

[...] Earned Value Management (EVM) provides valuable and universally accepted metrics for measuring a project’s performance to budget. The objective is to determine whether you have accomplished the project worked you planned for the budget you planned. Budget will include the cost of all goods, services, resources (human and non-human), and administrative services consumed by the project. There are several different ways of mining the metrics needed to perform these measurements. The simplest is the MS Project file for the project, which can track all these. MS Project shows money being spent at exactly the same rate as activity completion. The budget for the C++ programming is exactly 72% consumed when the C++ programming is 72% complete. This may not be what your audience is looking for. [...]

The Project Scorecard - PM Hut wrote on October 18, 2009 - 11:14 am | Visit Link

feel free to leave a comment

Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

All fields marked with " * " are required.

Project Management Categories