Not My Job (NMJ)

May 19, 2008 | Author: PM Hut | Filed under: People Issues

Not My Job (NMJ)
By Thomas Cutting

A project manager once came to me with an interesting dilemma. It seems the manager for one of her projects was asking her for status reports on projects she wasn’t even involved with. As she explained the situation it became clear that this manager had not assigned PMs to 3 or 4 projects that he was responsible for. She felt trapped. She couldn’t easily say, “Hey! That’s NMJ (Not My Job)!”

My suggested solution was to handle it like a change request. First, determine the amount of time spent on a weekly basis to gather, document and present the status for each project. Depending on the level of reporting this could be significant (i.e. progress reporting, financial reporting, issue and risk reporting, defect reports, etc.). For this PM the effort was compounded by the fact that she wasn’t remotely part of any of the projects.

Second, meet with the manager and explain the impact this is having on other projects. Show him the estimates and point out that these projects need their own PMs assigned that are able to do more than just report status. In essence, verbally issue a change request and ask if this should be made part of your project. This ought to be enough to make him see the problem and find a different solution.

However, if he insists the reporting continue you may have a decision to make: live with it or say, “No.” For the “just say no” side, I was once asked to add a fourth project to my workload. In that case I explained that I could not successfully manage another and declined. I know the manager was disappointed and I probably lost some of his respect, but I knew it wasn’t possible.

If your decision is to continue doing the reporting, at least make sure you are placed on the projects for time reporting or billing purposes so the effort is taken from the right budget. This will help hammer home the impact without killing the budget of your original project.

Thomas Cutting, PMP is the owner of Cutting’s Edge (http://www.cuttingsedge.com) and is a speaker, writer, trainer and mentor. He offers nearly random Project Management insights from a very diverse background that covers entertainment, retail, insurance, banking, healthcare and automotive verticals. He delivers real world, practical lessons learned with a twist of humor. Thomas has spoken at PMI and PSQT Conferences and is a regular contributor to several Project Management sites. He has a blog at http://cuttingsedgepm.blogspot.com.

Share this article:
  • Digg
  • del.icio.us
  • Facebook
  • Google
  • blogmarks
  • LinkedIn
  • Reddit
  • StumbleUpon
  • TwitThis
  • Yahoo! Buzz

No comments yet.

feel free to leave a comment

Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

All fields marked with " * " are required.

Project Management Categories