Project Management Tetris
August 9, 2012 | Author: PM Hut | Filed under: Project Management Musings
Project Management Tetris
By Brett Harned
I loved Tetris as a kid. I played the Gameboy version for hours. I now have it on my iPhone and iPad and find myself playing it when I’m on a flight, or bored, waiting for something to happen (which is never these days). Whether I’m playing the game a lot or not, the idea of making tiny boxes fit in neatly and clearing out rows of work in ingrained in my brain. It’s what I do on a daily basis when sorting out who will work on what; it’s what we often call “resourcing.” And it’s one of my biggest project management challenges, for sure.
The biggest difference between resourcing and Tetris? The team members we’re trying to assign tasks to aren’t blocks; they’re human beings and they need to be treated as such. To be honest, the term “resourcing” makes me cringe a little. We’re really just staffing projects or assigning tasks. We’re not using people to JUST get things done; We’re asking them to solve challenges that are presented in our projects. The thing is, even with a small team, you have to sort out who will do what when you have more than a few projects running concurrently. Everyone can’t be responsible for everything, and many people specialize in some tasks.
Level 1: Easy
So, how do I approach the challenge of making sure the team is busy and working on tasks, or not completely overbooked? It’s not fun, and I have yet to find the perfect tool to help me forecast hours. So, a couple of years back I put together a little spreadsheet that lists team members’ names, and the projects they’re on.
A couple of notes:
- The final cell tallies the hours for you. Snappy Excel or Numbers work!
-
You can track Actual hours if you’re like. It could help with future estimating. (Just pull that time out of your time tracking tool, if you have one.)
-
Check your estimates with your team to make sure that the hours actually align with their assessment of the task (This might help with avoiding that red number!)
-
Communicate these hours to the entire team each week. Making sure everyone “is in the know” will help on any project.

Here’s the thing: it’s not just about numbers. I mean, really. If you’re a project manager who thinks your estimates are always dead on or even realistic at all times, you should read some other articles then come back to this. The issue that makes estimating a team’s project hours is that everyone works differently. There is no way to standardize the human factor here, and that’s what makes it tough. Forget the fact that none of your team is a robot and they all work at their own pace. Think about sick days, vacations, client delays, changes on projects, etc. It’s a never-ending flow of shapes that must fit into the box that is a project.
Level 2: It’s Getting Faster!
It’s not easy to do, but you need to consider these things when trying to staff your projects:
- Interests: If you have a team member who loves beer, why not put that person on the beer design site? Maybe you have multiple people who want to be on the project, but they are all busy on other projects. These are the breaks. You’ve gotta do what is right for the company and your budget. If you can put interests first, it’s awesome. We try to do it, but it doesn’t always work that way.
-
Skill sets: It’s as simple as getting to know each and every team members’ work. Some people are meant to create specific types of designs or experiences. It not only has to do with interests, it has to do with strengths within those tasks. Sure, I may love beer, but that doesn’t mean that I am meant to design the site that caters to the audience the client is trying to reach.
-
Moving schedules: Projects will always change. One week you know you’re working against a firm deadline, and the next, that has changed due to the clients, the needs of the project, or some other reason someone conjured up. IT’s tough to know when that change will happen, but when it does, how you’ll fill someone’s time should be high on your check list.
Holidays: People always extend them. Plan for that! -
Vacations: It’s great to know in advance. Be sure you know your company’s policies around that. I never ever want to be the guy who says, “Well, you have a deadline on X date and that will conflict with your cruise, so, um…no.” I’d rather plan ahead and make it work. Everyone would.
-
Illness: God forbid someone get sick! You’ve always got to be ready for a back up plan with clients. It shouldn’t fall on the clients to make up time, but sometimes it has to. Or, sometimes you need to look for someone to pitch in on intermediate tasks to keep thinks on track while your “rock star” or “ninja” is getting better.
Level 3: OMG They’re Stacking Up!
So, what about when you’re considering new projects that will put you over your team’s capacity? Planning your resource hours out to the end of your most recent project makes a lot of sense. But, if you’ve got a sales pipeline to consider, it can get tricky. The best thing to do, in my opinion, is to be flexible, chat with your team about options, and handle the issues as they come to you. You might have to consider freelancers, or possibly bringing up the need to hire someone.
At the end of the day, making sure that we’re staffed at the right levels all the time is probably one of my biggest challenges. I think there are some solid ways to make sure we’re 90% of the way there, but it can be tough. Want to share your thoughts? Your highest scores in Tetris? Post a comment below. I’d love to hear from you.
Brett Harned’s fascination with the creative process and his passion for concise communication, strategy, and attention to detail means that his clients get a project manager who immerses himself in the work product, not just timelines and milestones. Brett’s deep understanding of web process and his ability to apply methodologies to any project makes clients happy. He is also adept at translating the language of web design to clients, which can sometimes get confusing and conceptual.
Brett manages projects large and small, and all of them receive the same level of care and dedication. Zappos.com, the United States Holocaust Memorial Museum, the National Constitution Center, and the Presbyterian Church (USA) are among some of the clients Brett has had the privilege to work directly with at Happy Cog.
Prior to joining Happy Cog, Brett served as Senior Project Manager at Razorfish. There, he managed large multi-disciplinary teams and implemented creative strategies resulting in websites and comprehensive digital advertising campaigns for companies such as Wyeth Pharmaceuticals and Aetna.
If there is one thing that Brett will tell you, it’s that project managers are not robots. Sure, they might rely on dates and numbers, but they have hearts too! Part of the Philly-based Happy Cog team, Brett practices what he preaches on his blog about his own adventures in project management, which can be found at http://brettharned.com.
When Brett isn’t wrangling timelines and budgets in the office, he likes to discover new music, experiment with photography, and explore the City of Brotherly Love with his wife and two daughters.
No comments yet.
feel free to leave a comment
Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!
XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
All fields marked with " * " are required.