Schedule Game #8: Pants on Fire (#8 in the series Schedule Game)
By Johanna Rothman
You’re a project manager. Your project is proceeding fairly well. You’ve had a few bumps, but you’re making progress. You come into work one day, and there’s a message to meet with the Big Cheese. Big Cheese says, “Stop working on that project. Start on this one!”
Not only does this happen once, it happens several times, either bouncing you and the project team among several projects, or back and forth between two projects. Whatever the circumstances, you’re multi-project multi-tasking, and so are all the people on your project team. You know you’re not making progress on anything, and the urgency of all the projects keeps going up and up and up…
This schedule game is called “Pants on Fire.” It occurs when management is afraid to focus on one thing at a time. It has several possible causes: when the technical staff has a track record of being late, when there’s no corporate strategy, or when the corporate strategy hasn’t been broken down into sufficiently-detailed tactics.
Some actions you can take:
- Plan for iterations, and start something new on an iteration boundary. To make this work, the iterations have to be short enough to start something new. (I’ve made a staged delivery lifecycle work in a company that was addicted to Pants on Fire management.)
- Help management develop a corporate strategy.
- Help test the tactics against the strategy.
- Modify your current estimation techniques, so the project team is more likely to meet their original estimated dates.
Pants on Fire wastes everyone’s time. But sometimes, management either cannot change their management style or cannot believe that multiprojecting wastes time. If you’re in a situation like that, consider how you can create a project-wide environment that allows you and your project team to work successfully.
Johanna Rothman consults, speaks, and writes on managing high-technology product development. Johanna is the author of Manage It!’Your Guide to Modern Pragmatic Project Management’. She is the coauthor of the pragmatic Behind Closed Doors, Secrets of Great Management, and author of the highly acclaimed Hiring the Best Knowledge Workers, Techies & Nerds: The Secrets and Science of Hiring Technical People. And, Johanna is a host and session leader at the Amplifying Your Effectiveness (AYE) conference (http://www.ayeconference.com). You can see Johanna’s other writings at http://www.jrothman.com.
Related Articles
No comments yet.
feel free to leave a comment
Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!
XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
All fields marked with " * " are required.