The WBS is Over-Rated

June 19, 2007 | Author: PM Hut | Filed under: Project Plan Development

The WBS is Over-Rated
By PMConnection

I’m sure this title gets all the PMI® big wigs a little edgy! And for all of those PMBOK toters, you can now pick up your book (as I’m sure it just hit the floor!) and read the following article about real world project management.

What is a WBS?

WBS stands for Work Breakdown Structure. Examining PMBOK®, we see that the WBS should be created after the scope of the project has been defined. Creating a WBS involves subdividing the major project deliverables and project work into smaller more manageable components. (PMBOK pg 49)

The planned work contained in the lowest-level WBS components are called Work Packages (PMOK® pg 112)

We can all agree with this, right?

But here’s the piece that most people miss, or don’t fully realize when talking about developing a WBS; the Work Packages should be decomposed one level farther to determine the Activities. (PMOK® pg 127) This step is like “the missing link”; connecting the WBS to your Schedule Network Diagram (or MS Project). This is formally called Activity Definition.

What is Activity Definition?

Activity Definition is the process of identifying and documenting the work that is planned to be performed. (PMOK® pg 127) And once we know the scope of our project, isn’t this the next biggest question; “What do we have to do to complete this project?”

So why is the WBS Over-Rated?

Well, if you are studying for the PMP exam or about to undertake a large project, it is not. It is very important.

But the WBS is nothing more than a tool. A tool to help you determine the activities that need to occur to complete the project.

So now lets examine this scenario; You have been assigned as the project manager for some project. The scope is well defined and the project sponsor as well as management believe this project could be completed in 3-6 months. Your team of 6 Subject Matter Experts has been determined. You have transferred the vision (scope) of this project to your team and are now about to hold your first planning session. All SME’s will participate in this meeting. Given this scenario, a formal WBS may be over-kill. A simple brainstorming session with the team could allow you to determine all the project activities. In short, you will be performing Activity Definition without the need for a formal WBS.

You may even be able to perform Activity Sequencing during the same session! This is the process of putting all of the activities in sequential order by establishing the logical relationship between the various activities. And inevitably, this process of Activity Sequencing (especially when completed with the team), will uncover more activities that need to occur.

Closing

In closing, I’d just like to state that I’m not advocating eliminating the development of a WBS, I’m merely stating that in many real world projects, a formal WBS may not be needed. I believe project management tools and processes should be scaled to fit the project. And if the detailed activities of the project can be determined without the need for additional work, then why do it?

PMConnection provides tons of Free information on Project, Program and Portfolio Management as well as MS Project, Project Server, PMO’s and the PMP.

They are proud to host the “most comprehensive list of Project Management and Microsoft Project related events found anywhere!”

Be sure to sign up for the free monthly newsletter.

Share this article:
  • Digg
  • del.icio.us
  • Facebook
  • Google
  • blogmarks
  • LinkedIn
  • Reddit
  • StumbleUpon
  • TwitThis
  • Yahoo! Buzz

Related Articles

No comments yet.

feel free to leave a comment

Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

All fields marked with " * " are required.

Project Management Categories