What is the PMP Exam Passing Score?
January 21, 2008 | Author: PM Hut | Filed under: Certification, PMP
What is the PMP Exam Passing Score?
By Cornelius Fichtner, PMP
The PMP® exam is a 4-hour multiple choice exam. In these 4 hours, you are going to have to answer 200 questions. Each question is either scenario based or knowledge based and has 4 possible answers - A, B, C or D. You can only select one answer.
Out of these 200 questions, 25 are considered “pretest questions”. These pretest questions do not affect your score. The PMI uses them as an effective and legitimate way for testing the questions. In other words: new questions for the exam are first tried out in this way, to see how well they work. The pretest questions are randomly placed throughout the exam.
So you start out with 200 questions minus the 25 pretest questions which leaves 175 questions. Out of these, you must answer 106 correctly. That is 61%.
If you would like more details on this, then I recommend that you read the PMP Credentials Handbook which you can find at this location: http://www.pmi.org/PDF/PDC_PMPHandbook.pdf.
Cornelius Fichtner, PMP is the host of The Project Management Podcast™ at www.thepmpodcast.com and The Project Management PrepCast™, the first true PMP® Podcast at www.pmprepcast.com. Cornelius worked as a Project Manager in his native Switzerland, in Germany and in the USA for the last 17 years. He received his PMP credential in April 2004. He has led projects for a management consulting company, a national retailer and an internet startup company. Currently, Cornelius works as a project manager for one of the oldest financial service providers in the USA. His passions are project management methodologies, PMOs and helping others pass the PMP Exam. In addition to hosting the PrepCast™, he is an instructor for the PMP Workshop and the 2007 Chair of his local PMI chapter. He currently lives in Silverado, California, USA with his wife and their two computers.
Related Articles
- Tips for Passing the PMP Exam
- Tips on Applying for and Passing the PMP® or CAPM® Exam - Part III - PMP Application
- Tips on Applying for and Passing the PMP® or CAPM® Exam - Part I - Introduction
- An 8 Point Plan For Passing The PMP Or CAPM Exam - PMP And CAPM Exam Simulation
- Tips on Applying for and Passing the PMP® or CAPM® Exam - Part VI - Types of Questions
feel free to leave a comment
Comment Guidelines: Basic XHTML is allowed (a href, strong, em, code). All line breaks and paragraphs are automatically generated. Off-topic or inappropriate comments will be edited or deleted. Email addresses will never be published. Keep it PG-13 people!
XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
All fields marked with " * " are required.











5 people have left comments
I saw that in 2005 the passing score was 106 out of 175, or 61%. Is that still true??
Thanks
M,
Yes, it still holds true (I check regularly), the PMP Passing Score is still 61%.
The Handbook on PMP does not specify the pass percentage. Then how are you arriving at 61%.
Sri,
If you calculate the number of questions that you need to answer correctly out of the 200, you’ll see that it’s 61%.
The handbook does not mention how many questions need to be answered correctly, it only states that 25 of the 200 questions are pre-test and not counted. So you’re right in that 175 questions are graded, however, where did you get the 61%?